Title: Relatório de estágio integrado - Borborema Energética S.A.
Other Titles: Integrated internship report - Borborema Energética S.A.
???metadata.dc.creator???: BARBOSA JÚNIOR , Antonio Nilton.
???metadata.dc.contributor.advisor1???: SILVA, Célio Anésio da.
???metadata.dc.contributor.referee1???: OLIVEIRA, Leimar de.
Keywords: Estágio em Engenharia Elétrica;Borborema Energética S.A;Usina termelétrica;Manutenção em geradores;Vazamento de gás SF6 em disjuntor;Lista de inspeção - elaboração;Internship in Electrical Engineering;Borborema Energética S.A.;Thermoelectric plant;Maintenance on generators;SF6 gas leak in circuit breaker;Inspection list - preparation
Issue Date: 2017
Publisher: Universidade Federal de Campina Grande
Citation: BARBOSA JÚNIOR, Antonio Nilton. Relatório de estágio integrado - Borborema Energética S.A. 2017. 31f. (Relatório de Estágio Integrado) Curso de Bacharelado em Engenharia Elétrica, Centro de Engenharia Elétrica e Informática, Universidade Federal de Campina Grande - Paraíba - Brasil, 2017. Disponível em: http://dspace.sti.ufcg.edu.br:8080/jspui/handle/riufcg/20016
???metadata.dc.description.resumo???: Neste relatório apresenta-se as principais atividades desenvolvidas durante o estágio integrado realizado na usina termoelétrica Borborema Energética S.A. - BESA pertencente ao grupo Bolognesi e localizada no município de Campina Grande - PB. O estágio integrado foi realizado no setor elétrico da empresa, onde foram realizadas atividades relacionadas a manutenções periódicas de vários equipamentos da planta, manutenção da subestação 230 kV, desenvolvimento e correção de procedimentos operacionais, detecção de vazamento de gás em disjuntor de alta tensão, acompanhamento dos técnicos em serviços elétricos, além do estudo dos vários setores da empresa buscando conhecer melhor o seu funcionamento. Durante o estágio foi possível aprimorar os conhecimentos aprendidos durante a graduação, além de ganhar experiência tanto pessoal quanto prática, consolidando o aluno profissionalmente parar enfrentar com segurança os desafios da profissão.
Abstract: This report presents the main activities developed during the internship carried out at the thermoelectric power plant Borborema Energética S.A. – BESA belonging to Bolognesi group. Located at the city of Campina Grande – PB. The intern has worked in the electrical sector of the company, the developed activities were related to periodic maintenance of equipment, maintenance of the substation of 230 kV, elaboration and adjustment of operational procedures, monitoring of technicians working on electrical service, besides of studying many sectors of the company to get a better understanding of its operations. Along the internship was possible to improve all knowledge acquired during graduation period, also get practical and personal experience, making of the student into a capable professional to face the challenges of the profession with confidence.
Keywords: Estágio em Engenharia Elétrica
Borborema Energética S.A
Usina termelétrica
Manutenção em geradores
Vazamento de gás SF6 em disjuntor
Lista de inspeção - elaboração
Internship in Electrical Engineering
Borborema Energética S.A.
Thermoelectric plant
Maintenance on generators
SF6 gas leak in circuit breaker
Inspection list - preparation
???metadata.dc.subject.cnpq???: Engenharia Elétrica.
URI: http://dspace.sti.ufcg.edu.br:8080/jspui/handle/riufcg/20016
Appears in Collections:Curso de Bacharelado em Engenharia Elétrica - CEEI - Relatórios de Estágio

Files in This Item:
File Description SizeFormat 
ANTONIO NILTON BARBOSA JÚNIOR - RELATÓRIO DE ESTÁGIO ENG. ELÉTRICA 2017.pdfAntonio Nilton Barbosa Júnior - Relatório de Estágio Eng. Elétrica 2017.2.02 MBAdobe PDFView/Open


Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.