BALBINO, T. S.; http://lattes.cnpq.br/8933636494784178; BALBINO, Tiago da Silva.
Resumo:
This report presents the activities carried out under the integrated stage performed in the
company Viridis Engenharia in the period from 14 July to 30 November 2014. Initially
some basic concepts of photovoltaic power generation and System Protection Lightning
(SPL), then describes the activities carried out during the probationary period, as
follows, the project photovoltaic microgeneration of condominium Atmosphera ECO
Residence in Lagoa Seca - PB, photovoltaic installations of the parking of the
Termope\Suape - PE and LEPER\UFRN in Natal, Brazil, installation of an inverter in
the Systems Laboratory Photovoltaic - UFCG Campus in the Campina Grande - PB,
monitoring and supervision of the electrical installations of Ernani Satiro stadium in
Campina Grande - PB, quotations and upgrade of quotes, equipment, materials and
services to automatization system adductors for CAGEPA, quotations of prices
equipment, materials and services for SPL the Launch Center Barreira do Inferno
(LCBI) in Parnamirim - RN and inspection and preparation of the appraisal report the
SPL from EPASA in João Pessoa – PB.