ARRUDA, M. M.; http://lattes.cnpq.br/3299838657781132; ARRUDA, Milena Marinho.
Resumen:
This document, presented as a report, describes in a sequential way the main
activities developed by the student in cooperation with the Rocha Asfalto – Indústria de
Asfalto, Locação de Equipamentos e Terraplanagem LTDA, that represents the
internship, that took place between June and December(08/06 – 05/12) of the current
year. With emphasis in the Electrotechnical area, the work that took place on the very
own mining field, was diversified in several tecnical anda administrative activities of
engineering, contemplating the effective follow up of the plant whole production
process, as well as, of the planning and control of the productive flow. Furthermore,
based on standardized documentation and relating to electrical installations for low and
medium voltage, as well as standards and specifications for distribution materials,
developed was a feasibility study for construction of a substation 1000 kVA / 13.8 kV,
to be implanted in the crushing unit of the company, in order to meet the specific
demands of its production process.