The purpose of this report is to describe, in a summarized way, the knowledge
acquired, as well as the activities carried out during the supervised internship at the
company Energy Eletricidade Ltda, a company in the field of design and execution of
electrical projects. The internship period was comprised between September 14, 2018 and
January 11, 2019. The activities carried out by the trainee focused on the participation of
the 34.5 / 69 kV substation of the Sol do Futuro photovoltaic plant, a 69 kV transmission
line connecting the substation to the Aquiraz II substation of Chesf in the city of Aquiraz-
CE , and in planning activities for the installation of the 3rd Trafo of 239/69 kV at the
Zebu II substation of Chesf in the city of Delmiro Gouveia-AL.