GAMA, Anne Caroline Marinho.
Abstract:
The application of cost engineering principles and techniques proves to be
of extreme
importance for the elaboration of assertive budgets, with great importance
in the organization of notices necessary for the bidding processes of the administration
public sector, contributing to a better management of public resources in view of a
social benefit. A tool in the engineering sector widely used as a basis
for calculating the cost of public works is the National Cost Research System
and Civil Construction Indexes – SINAPI. This research aims to analyze the budget of
construction of a sports court in the municipality of Pombal - PB, from
comparing budgets for the years 2021 and 2022, with the
reference to the National Research System of Civil Construction Costs and Indexes
(SINAPI). To respond to the proposed objective, a
price update,
in September 2022, based on the budget for said work, produced in February
of 2021 and made available in public notice 0005/2021 of the Municipality of PombalPB,
using the same SINAPI compositions. Then dismember
The
synthetic budget worksheet in order to extract the inputs and labor for
collect prices according to the local market, generating a spreadsheet
budget with these values. With the three worksheets in hand, we proceeded
one
comparative analysis of budgeted prices. The results of this research point to
a 23.63% increase in the difference between the amounts budgeted in 2021 and 2022, as of
of the SINAPI system. This variation is symptomatic with regard to the instability of the
market due to the pandemic period that considerably affected the
construction. observed
also that, in the comparison between the worksheet
budget of the referred public notice and the spreadsheet updated with local prices, there was
an increase of 16.12%. In addition to the issue of the volatile market in the context of
pandemic, in this case, the delay in the bidding procedures also contributes to this
disparity. In the comparative analysis of the updated spreadsheets, it was observed
one
6.07% advantage for the budget produced through SINAPI, which corroborates
the viability of this tool for bidding public works in the backlands of Paraíba.